The supercharger assembly will require the help of an assistant(s) to install the assembly into the engine compartment.
- Inspect the seals and replace if necessary.
- Position the supercharger assembly onto the cylinder heads, aligning the dowels in the supercharger with the holes cylinder head.
- Using the sequence shown, Install the supercharger retaining bolts and tighten all retaining bolts as follows:
- First tighten all bolts, using the sequence, to 5 N.m (4 ft. lbs.).
- Next tighten all bolts, using the sequence, to 15 N.m (11 ft. lbs.).
- Finally tighten all bolts, using the sequence, to 30 N.m (22 ft. lbs.).
- Connect the fuel supply line (1) to the fuel rail (2). Refer to FITTING, QUICK CONNECT, STANDARD PROCEDURE
.
- Install the Low Temperature Radiator (LTR) circuit hoses to coolant crossover (1).NOTE:
Use previous markings to determine hose location.
- Connect the wire harness connector to the charger air cooler temperature sensor, located on the crossover tube.
- Connect the fuel injector wire harness connectors (1) on both sides of supercharger.
- Connect the wire harness connector (2) to the intermediate Temperature-Manifold Absolute Pressure (TMAP) sensor (1).
- Connect the wire harness connector (2) to the bank two TMAP sensor (3).
- Connect bank one (1) and throttle outlet (2) TMAP sensor wire harness connectors.
- Connect the wire harness connector to the throttle body at nose of supercharger.
- Connect the bypass valve wire harness connector (3).
- Install the Positive Crankcase Ventilation (PCV) hose (1) to the right side of supercharger nose (2).
- Install the fuel purge hose (2) to the top of the supercharger nose (1).
- Install the brake booster hose, located under the nose of the supercharger.
- Install the supercharger belt. Refer to BELT, DRIVE, INSTALLATION .
- Install the engine covers.
- Install the air cleaner body Refer to BODY, AIR CLEANER, INSTALLATION
.
.
- Install the cowl cover panel. Refer to COVER, COWL PANEL, INSTALLATION .
- Fill the cooling system. Refer to STANDARD PROCEDURE
.NOTE:
Evacuating or purging air from the charge air cooling system must be done with the use of a pressurized air operated vacuum generator.
- Connect the negative battery cable.